• Language:
Consulting Services for Urgent Upgrading of Colombo Port Project (North Channel Dredging) (Improvement of Container Yard of JCT No. 1 and No. 2)

Objective of the project is to enhance the efficiency of container handling in Jaya Container Terminal (JCT) by execution of the following improvement works for container yard of JCT No. 1 and No. 2 

Assignment Name:

Consulting Services for Urgent Upgrading of Colombo Port Project (North Channel Dredging) (Improvement of Container Yard of JCT No. 1 and No. 2)

Country:

Sri Lanka

Location within Country:

Colombo

Professional Staff Provided by Your Firm:

Project Manager, Port Engineer

Name of Employer:

Sri Lanka Ports Authority (SLPA), Gov. of Sri Lanka

No. of Staff:

2

Address:

No. 19, Church Street, Colombo 1, Sri Lanka         

No. of Staff-Months:

15 M/M

Start Date (Month/Year):

June 21, 2004

Completion Date (Month/Year):

 September 20, 2005

Approx. Value of Services

(in Current US$):

USD 251,920

Duration of the Services:

  15.0 Months

Name of Associated Consultants, if any:

  N/A

No. of Months of Professional Staff Provided by Associated Consultants:

N/A

Name of Senior Staff (Project Director/Coordinator, Team Leader) involved and functions performed:

K. Sasaki / T. Ichizono : Project Manager

Approximate Total Value of the Project:

USD 24 Million

Narrative Description of Project:

Objective of the project is to enhance the efficiency of container handling in Jaya Container Terminal (JCT) by execution of the following improvement works for container yard of JCT No. 1 and No. 2 :

1)      Change of the original asphalt paving;

2)      Raising of the prestressed concrete track lane of transfer cranes to the correct level;

3)      Adjustment of PC slab joints;

4)      Repair of deteriorated yard area;

5)      Yard marking; and

6)      Repair of damaged PC slabs.

Description of Actual Services Provided by Your Staff:

Consulting services provided by our staff cover the following :

1)      Issue of Variation Orders required for the additional works to the Contractor;

2)      Detailed design and preparation of Technical Specifications and Bills of Quantities;

3)      Supervision of construction works;

4)      Preparation of Progress Report and Completion Report; and

5)      Issue of Taking-Over Certificate to the Contractor.

[ Back]