Assignment Name:
Consulting Services for Urgent Upgrading of Colombo Port Project (North Channel Dredging) (Improvement of Container Yard of JCT No. 1 and No. 2)
|
Country:
Sri Lanka
|
Location within Country:
Colombo
|
Professional Staff Provided by Your Firm:
Project Manager, Port Engineer
|
Name of Employer:
Sri Lanka Ports Authority (SLPA), Gov. of Sri Lanka
|
No. of Staff:
2
|
Address:
No. 19, Church Street, Colombo 1, Sri Lanka
|
No. of Staff-Months:
15 M/M
|
Start Date (Month/Year):
June 21, 2004
|
Completion Date (Month/Year):
September 20, 2005
|
Approx. Value of Services
(in Current US$):
USD 251,920
|
Duration of the Services:
15.0 Months
|
Name of Associated Consultants, if any:
N/A
|
No. of Months of Professional Staff Provided by Associated Consultants:
N/A
|
Name of Senior Staff (Project Director/Coordinator, Team Leader) involved and functions performed:
K. Sasaki / T. Ichizono : Project Manager
|
Approximate Total Value of the Project:
USD 24 Million
|
Narrative Description of Project:
Objective of the project is to enhance the efficiency of container handling in Jaya Container Terminal (JCT) by execution of the following improvement works for container yard of JCT No. 1 and No. 2 :
1) Change of the original asphalt paving;
2) Raising of the prestressed concrete track lane of transfer cranes to the correct level;
3) Adjustment of PC slab joints;
4) Repair of deteriorated yard area;
5) Yard marking; and
6) Repair of damaged PC slabs.
|
Description of Actual Services Provided by Your Staff:
Consulting services provided by our staff cover the following :
1) Issue of Variation Orders required for the additional works to the Contractor;
2) Detailed design and preparation of Technical Specifications and Bills of Quantities;
3) Supervision of construction works;
4) Preparation of Progress Report and Completion Report; and
5) Issue of Taking-Over Certificate to the Contractor.
|