Narrative Description of Project:
This project is intended to construct a full fledged container terminal in Semarang Port to cope with the growing demand for efficient handling of the rapidly increasing container cargo. The project components include :
1) Container wharf (-10 m deep, 345 m long);
2) Retaining wall (407 m long);
3) Revetment (2,510 m long in total);
4) Container yard (7 ha) with CFS (3,600 m2), maintenance shop (1,600 m2), workshop (1,350 m2) and office buildings and utilities;
5) Navigation channel and basin dredging (2,096,000 m3);
6) Reclamation (650,000 m3);
7) Foundation improvement (106,000 m2); and
8) Access road (1 km long).
|