Assignment Name:
Detailed Design Study on Urgent Rehabilitation Project of Tanjung Priok Port in Indonesia (2nd Year)
|
Country:
Indonesia
|
Location within Country:
Tanjung Priok Port, Jakarta
|
Professional Staff Provided by Your Firm:
Dpy. Team Leader, Port Eng., Environmental Eng., etc.
|
Name of Employer:
Japan International Cooperation Agency (JICA)
|
No. of Staff:
5
|
Address:
1-1, Yoyogi 2-chome, Shibuya-ku, Tokyo, Japan
|
No. of Staff-Months:
29.4 M/M
|
Start Date (Month/Year):
April 7, 2005
|
Completion Date (Month/Year):
March 20, 2006
|
Approx. Value of Services (in Current US$):
Total : USD 3,357,9105
JPC Share : USD 840,927
|
Duration of the Services:
11.5 Months
|
Name of Associated Consultants, if any:
JV Leader : Nippon Koei Co., Ltd. (NK)
JV Partner : Japan Port Consultants, Ltd. (JPC)
|
No. of Months of Professional Staff Provided by Associated Consultants:
34.9 M/M
|
Name of Senior Staff (Project Director/Coordinator, Team Leader) involved and functions performed:
K. Ohkubo : Team Leader (NK)
M. Imamura : Deputy Team Leader / JPC Team Leader
|
Approximate Total Value of the Project:
USD 142 Million
|
Narrative Description of Project:
Objective of the study is to conduct the detailed design, including all necessary documentations, of the following project facilities :
Channel and Basin Improvement
1) Dam Tengah Breakwater (new construction : 1,1561 m, demolition : 1,605 m);
2) Dam Barat Breakwater (new construction : 100 m, demolition : 225 m); and
3) Improvement of existing navigation channel and port basin, channel and basin dredging (8,078,000 m3) and navigation aids.
Inner Port Road Improvement
1) Improvement of inner access road (3,500 m);
2) Flyover construction (650 m); and
3) Utility works.
|
Description of Actual Services Provided by Your Staff:
The consulting services provided by our staff cover the following :
1) Supplementary surveys on present conditions of the port, natural conditions surveys, environmental surveys and EIA;
2) Basic designs and preparation of Basic Design Report and Definitive Plan;
3) Detailed design and detailed construction planning, including cost estimate;
4) Preparation of Prequalification and Bidding Documents, and Implementation Program;
5) Formulation of Environmental Management Plan and facility operation & management plan;
6) Preparation of Design Report, Progress Reports (1) and (2), Draft Final Report, and Final Report.
|