Detailed Design Study on Urgent Rehabilitation Project of Tanjung Priok Port in Indonesia (1st Year)

Objective of the study is to conduct the detailed design, including all necessary documentations, of the following project facilities :

Channel and Basin Improvement

1)       Dam Tengah Breakwater (new construction : 1,1561 m, demolition : 1,605 m);

2)       Dam Barat Breakwater (new construction : 100 m, demolition : 225 m)

3)       Improvement of existing navigation channel and port basin, navigation channel and basin dredging (8,078,000 m3) and installation of navigation aids.

Assignment Name:

Detailed Design Study on Urgent Rehabilitation Project of Tanjung Priok Port in Indonesia (1st Year)

Country:

Indonesia

Location within Country:

Tanjung Priok Port, Jakarta

Professional Staff Provided by Your Firm:

Deputy. Team Leader, Port Eng., and Environmental Eng.

Name of Employer:

Japan International Cooperation Agency (JICA)

No. of Staff:

  3

Address:

1-1, Yoyogi 2-chome, Shibuya-ku, Tokyo, Japan

No. of Staff-Months:

3.9 M/M

Start Date (Month/Year):

January 27, 2005

Completion Date (Month/Year):

March 31, 2005

Approx. Value of Services (in Current US$):

Total : USD 396,596

JPC Share : USD 108,266

Duration of the Services:

  2.1 Months

Name of Associated Consultants, if any:

  JV Leader : Nippon Koei Co., Ltd. (NK)

  JV Partner : Japan Port Consultants, Ltd. (JPC)

No. of Months of Professional Staff Provided by Associated Consultants:

  5.9 M/M

Name of Senior Staff (Project Director/Coordinator, Team Leader) involved and functions performed:

K. Ohkubo : Team Leader (NK)

M. Imamura : Deputy Team Leader / JPC Team Leader

Approximate Total Value of the Project:

USD 142 Million

Narrative Description of Project:

Objective of the study is to conduct the detailed design, including all necessary documentations, of the following project facilities :

Channel and Basin Improvement

1)       Dam Tengah Breakwater (new construction : 1,1561 m, demolition : 1,605 m);

2)       Dam Barat Breakwater (new construction : 100 m, demolition : 225 m)

3)       Improvement of existing navigation channel and port basin, navigation channel and basin dredging (8,078,000 m3) and installation of navigation aids.

Inner Port Road Improvement

1)       Improvement of inner access road (3,500 m)

2)       Flyover construction (650 m)

3)       Utility works

Description of Actual Services Provided by Your Staff:

The consulting services provided by our staff cover the following :

1)       Collection and analysis of relevant data, information and reports;

2)       Study on basic policy, method time schedule and sequence of the study;

3)       Preparation of Inception Report;

4)       Natural conditions surveys and EIA; and

5)       Preparation of work report for the first year study.