Consulting Service for Initial Feasibility Study to Waterway Transport System in Hochiminh City
|
Vietnam
|
Uni-Bros. Group
|
2011
|
114.488
|
Navigation Aids, Dredging, Reclamation, Wharf, Yard, Building, Utility, Equipment, Service Vessel.
|
-
|
Consulting Services for Detailed Design of Seaport under Dong Lam Cement Plant Project
|
Vietnam
|
International Transportation Investment & Development JSC.
|
2011
|
340,789
|
Navigation Aids, Dredging,Breakwater, Reclamation, Wharf, Yard, Building, Utility, Equipment, Service Vessel, Road, Bridge.
|
-
|
Consulting Services for Detailed Design of Cua Lo Deep Sea Port Expansion Development Project in Nghe An Province
|
Vietnam
|
International Transportation Investment & Development JSC.
|
2011
|
634,227
|
Dredging,Breakwater, Reclamation, Wharf, Yard, Building, Utility, Equipment, Service Vessel, Road, Bridge.
|
-
|
Consulting Services for Feasibility Study and Basic Design of Cua Lo Deep Sea Port Expansion Development Project in Nghe An Province
|
Vietnam
|
International Transportation Investment & Development JSC.
|
2010
|
287,144
|
Dredging,Breakwater, Reclamation, Wharf, Yard, Building, Utility, Equipment, Service Vessel, Road, Bridge.
|
-
|
Consulting Services for Master Plan and Conceptual Design of Cua Lo Deep Sea Port Expansion Development Project in Nghe An Province
|
Vietnam
|
TH Transportation JSCo.
|
2010
|
161,575
|
Dredging,Breakwater, Reclamation, Wharf, Yard, Building, Utility, Equipment, Service Vessel, Road, Bridge.
|
-
|
Consulting Services for Feasibility Study of Seaport under Dong Lam Cement Plant Project
|
Vietnam
|
Dong Lam Cement JSCo.
|
2009
|
404,000
|
Navigation Aids, Dredging,Breakwater, Reclamation, Wharf, Yard, Building, Utility, Equipment, Service Vessel, Road, Bridge.
|
-
|
Consulting Services for Port Master Plan and Feasibility Study for Sao Mai – Ben Dinh Petroleum Marine Logistic Base Project
|
Vietnam
|
Sao Mai – Ben Dinh Petroleum Investment Joint Stock Company (PVSB)
|
2008
|
324,000
|
General Cargo Port, Outfitting Jetties; Channel and Basins, DryDock and Lifting Facility for Ship Repair and Ship Construction, Port for Service Vessels.
|
-
|
Consulting Services for Cai Mep – Thi Vai International Port Construction Project
|
Vietnam
|
Gov. of Vietnam / Japan Bank for International Cooperation (JBIC)
|
2007-2014
|
10,632,562
|
River Channel, Navigation Aids, VTS, Dredging, Reclamation, Foundation Improvement,Wharf, Yard, Building, Utility, Equipment, Road, Bridge, EIA
|
-
|
Project Supervision Consultancy (for Development and Build of Proposed Thi Vai International Port Comprising Two (2) Numbers of Multipurpose Berths for 80,000 DWT Vessels including Ancillary Facilities)
|
Vietnam
|
SP-PSA International Port Co., Ltd. / Own Fund
|
2007-2009
|
642,760
|
Dredging, Reclamation, Foundation Improvement,Wharf, Yard, Building, Utility, Equipment, Road
|
10.
|
Detailed Design Study of Cai Mep – Thi Vai International Terminals in Vietnam (1st Year)
|
Vietnam
|
Japan International Cooperation Agency (JICA)
|
2004-2005
|
4,523,747
|
River Channel,Navigation Aids, VTS, Dredging, Reclamation, Foundation Improvement,Wharf, Yard, Building, Utility, Equipment, Road, Bridge, EIA
|
11.
|
Detailed Design Study of Cai Mep – Thi Vai International Terminals in Vietnam (2nd Year)
|
Vietnam
|
JICA
|
2005-2006
|
3,265,810
|
River Channel,Navigation Aids, VTS, Dredging, Reclamation, Foundation Improvement,Wharf, Yard, Building, Utility, Equipment, Road, Bridge, EIA
|
12.
|
Study on Red River Inland Waterway Transport System in Vietnam (1st Year)
|
Vietnam
|
JICA
|
2001-2002
|
1,059,423
|
River Channel, Navigation Aids,Dredging, Reclamation,Wharf, Yard, Building, Utility, Equipment, Road, IEE
|
13.
|
Study on Red River Inland Waterway Transport System in Vietnam (2nd Year)
|
Vietnam
|
JICA
|
2002-2003
|
1,847,333
|
River Channel, Navigation Aids,Dredging, Reclamation,Wharf, Yard, Building, Utility, Equipment, Road, IEE
|
14.
|
Port Development Study in South of Vietnam (1st Year)
|
Vietnam
|
JICA
|
2001-2002
|
2,771,607
|
River Channel, Navigation Aids,Dredging, Reclamation, Foundation Improvement,Wharf, Building, Yard, Utility, Equipment, Road, EIA
|
15.
|
Port Development Study in South of Vietnam (2nd Year)
|
Vietnam
|
JICA
|
2002-2003
|
1,320,233
|
River Channel,Navigation Aids,Dredging, Reclamation, Foundation Improvement,Wharf, Building, Yard, Utility, Equipment, Road, EIA
|
16.
|
Consulting Services for Da Nang Port Improvement Project
|
Vietnam
|
Gov. of Vietnam / Overseas Economic Fund of Japan (OECF)
|
2000-2006
|
8,032,505
|
Navigation Aids, Dredging,Breakwater, Reclamation, Foundation Improvement,Wharf, Yard, Building, Utility, Equipment, Service Vessel, Road, Bridge, EIA
|
17.
|
OECF Special Assistance for Project Formation (SAPROF) for Da Nang Port Improvement Project
|
Vietnam
|
OECF
|
1998
|
507,223
|
Navigation Aids,Dredging,Breakwater, Reclamation, Foundation Improvement,Wharf, Yard, Building, Utility, Equipment, Service Vessel, Road, Bridge, IEE
|
18.
|
Study on Port Development Plan in Key Area of Central Region of Vietnam (1st Year)
|
Vietnam
|
JICA
|
1997
|
973,706
|
Navigation Aids,Dredging,Breakwater, Reclamation,Wharf, Yard,Building, Utility, Equipment, Service Vessel, Road, Bridge, EIA
|
19.
|
Study on Port Development Plan in Key Area of Central Region of Vietnam (2nd Year)
|
Vietnam
|
JICA
|
1997-1998
|
2,190,072
|
Navigation Aids,Dredging,Breakwater, Reclamation,Wharf, Yard,Building, Utility, Equipment, Service Vessel, Road, Bridge, EIA
|
20.
|
Study on Port Development Plan in Key Area of Central Region of Vietnam (3rd Year)
|
Vietnam
|
JICA
|
1998
|
216,236
|
Navigation Aids,Dredging,Breakwater, Reclamation,Wharf, Yard, Building, Utility, Equipment, Service Vessel, Road, Bridge, EIA
|